1 Chittagong Water Supply Improvement and Sanitation Project(CWSISP) 90 Mld Water Treatment Plant at Modunaghat
Modunaghat WTP to Nasirabad Reservoir (45 MLD 900 dia, 12 Km.)
Modunaghat WTP to Kalurghat Booster Station (45 MLD 900 dia, 9 Km.)
Kalurghat Booster Station to Patenga Booster Station (25 MLD, 750 dia, 13 Km.)
Construction & Replacement works of Patenga in-line Booster Station
Drainage Master plan
Pilot Septic sludge system
Institutional & operational development and project management support
Project Cost: 170.0 million US$
Source of Fund: World Bank.
Will be completed on December,2018
2 Bandar-Juri water Supply Project 45 Mld water treatment Plant at south bank of river Karnaphuli.
Necessary transmission and Distribution Pipeline
3 Karnaphuli Water Supply Project (2nd Phase) Rangunia WTP (14 crore liter)
505 km Pipeline
Project Cost: 4492 crore
Will be completed on January, 2022